DDG 51 Modernization Program Meets Key Milestones

 

Mar 12, 2015 ASDNews Source : US Navy

 

The Navy's DDG 51 modernization program has met two key milestones Naval Sea Systems Command (NAVSEA) announced Dec. 22.

The milestones involve the successful installation and testing of the new Aegis baseline 9 combat system on two DDG 51 destroyers, and a hull, mechanical and electrical (HM&E) modernization to a third. The modernization program ensures Arleigh Burke-class ships keep pace with evolving threats while meeting service life requirements and future operational commitments.

 

Read more

Partager cet article
Repost0
10 octobre 2014 5 10 /10 /octobre /2014 11:20
Northrop Grumman Conducts Successful Demonstration of its AQS-24A Mine Detecting Sensor System for US Naval Forces Central Command

 

ANNAPOLIS, Md. – Oct. 6, 2014 – Northrop Grumman

 

Northrop Grumman Corporation (NYSE:NOC), in support of U.S. Naval Forces Central Command in Manama, Bahrain, announced the successful demonstration of an unmanned mine-hunting mission. In the demonstration, the Mine Hunting Unmanned Surface Vehicle (MHU) was used in tandem with Northrop Grumman's AQS-24A Mine Detecting Sensor System in the Arabian Gulf.

The demonstration highlighted the unmanned capabilities of the MHU in deploying, towing and recovering the AQS-24A.

The MHU with the AQS-24A was rapidly fielded by the U.S. Navy's Unmanned Maritime Systems Program Office (PMS406), NAVSEA, Naval Undersea Warfare Center (NUWC), Division Newport and Northrop Grumman to prove the utility of mine hunting from an 11-meter unmanned surface platform.

The MHU was remotely controlled and executed a preplanned mission by transiting to an operational area, deploying the AQS-24A, executing a search pattern and recovering the sensor. Real-time situational awareness data and sensor sonar data were sent via tactical data link to the command and control (C2) station to ensure safe operation while maintaining mission objectives.       

"We are encouraged by the progress made with MHU 1 and 2 in 5th Fleet," said Capt. David Honabach, PMS 406 Unmanned Maritime Systems program manager, U.S. Navy. "We are also pleased that we could successfully demonstrate this capability to a key coalition partner in the Arabian Gulf region and look forward to Flight 2 Mine Hunting Unmanned Surface Vehicles [USV] for future success."

"This Navy demonstration, along with the continued investments we are making across the USV and mine-hunting technology spectrum, demonstrate that Northrop Grumman is committed to assisting the Navy and our coalition partners in defeating the maritime mine threat while keeping sailors out of the minefield," said Tom Jones, vice president, Undersea Systems, Northrop Grumman.

The deployment of this technology expands the operational envelope of the AQS-24A to be expanded for day and night operations at lower operational costs. This reduces the time to clear ports, harbors, channels and sea lines of communications of threatening mines and other maritime navigation hazards. The success of the remotely operated MHU also removes the warfighter from being directly exposed to the dangers of mined areas.

 

Northrop Grumman is a leading global security company providing innovative systems, products and solutions in unmanned systems, cyber, C4ISR, and logistics and modernization to government and commercial customers worldwide. Please visit www.northropgrumman.com for more information.

Partager cet article
Repost0
8 mai 2013 3 08 /05 /mai /2013 07:20
The bow of the future USS Gerald R. Ford (CVN 78) was mounted on the ship in early April. The ship will remain in the drydock in which it was built until November.

The bow of the future USS Gerald R. Ford (CVN 78) was mounted on the ship in early April. The ship will remain in the drydock in which it was built until November.

 

May. 6, 2013 By CHRISTOPHER P. CAVAS  - Defense News

 

WASHINGTON — The launch of the US aircraft carrier Gerald R. Ford has been moved back from July to November, a consequence of production delays identified two years ago.

 

The move comes weeks after the US Navy and shipbuilder Newport News Shipbuilding moved the ship’s delivery from September 2015 — which has been the contracted date for some years — to early 2016.

 

“We've been tracking and reporting schedule risk for several years and actively working to retire that risk,” Chris Johnson, a spokesman for Naval Sea Systems Command (NAVSEA) said May 7 in an email. “Following a detailed review of the schedule in February 2013, the Navy and the shipbuilder concluded that a delay in the launch would allow the shipbuilder to complete the remaining critical path work and allow for increased outfitting to most economically complete the ship.”

 

Earlier, Johnson acknowledged the problems associated with the first ship of a new design.

 

“Certainly it’s not ideal, but in this case it is very much a first-of-class issue. And those ships have challenges.”

 

The Ford is the first of the CVN 78-class carriers, the first new US carrier design since the mid-1960s. The 100,000-ton ships — the largest warships in the world — are also the first to be entirely designed using computer-aided design technologies.

 

Newport News Shipbuilding, a division of Huntington Ingalls Industries, is the only shipbuilder in the world capable of building full-sized nuclear-powered aircraft carriers.

 

The shipbuilder, in a statement released Monday, acknowledged its problems in making up the schedule delays. HII’s statement in full:

 

“Working closely with the Navy, we have revised the Gerald R. Ford (CVN 78) launch date from July 2013 to November 2013. Although actions to resolve first-of-class issues have retired significant schedule risks, the revised launch date allows increased outfitting and ship construction that are most economically done prior to ship launch.

 

“As the first new design carrier beginning construction in more than 40 years, CVN 78 is designed to provide increased capability and reduced total ownership cost by about $4 billion compared to Nimitz-class carriers. For this first-of-class ship, construction commenced in parallel with design completion based on earlier decisions at [the] Department of Defense. Ongoing design during the construction process caused delay and inefficiencies in procurement, manufacturing, and assembly.

 

“We have demonstrated that delaying launch (and therefore delivery) to allow for increased outfitting and construction prior to launch is the most economical path forward to deliver the tremendous capability and affordability improvements resident in Ford. “

 

NAVSEA also released a statement on the shift in launch date:

 

“The CVN 78 launch date will be revised from July 2013 to November 2013, and delivery will be shifted to second quarter FY 2016. Although shipbuilder actions to resolve first-of-class issues have retired significant schedule risks to launch and stabilized schedule performance, they have not been able to overcome the 17 weeks of schedule pressure identified two years ago.

 

“The Navy and the shipbuilder concluded last month that a delay in the launch would allow the shipbuilder to complete the remaining critical path work and allow for increased outfitting to most economically complete the ship. The ship is expected to be 70 percent complete at launch, well prepared for subsequent shipboard testing.

 

“Ongoing design and new technology development during the construction process caused delays in material procurement, manufacturing and assembly.

 

“First-of-class producibility issues [that impacted the schedule included] the use of thinner steels which caused difficulties with structural erection; new processes for advanced coating systems; and qualification of new material components. The shipbuilder recommended a delay in launch in order to accomplish greater completion levels prior to launch and thereby enable the lead ship to be completed most economically. The Navy agreed.

 

“As reported by the Navy previously in its December 2011 CVN 78 Selected Acquisition Report, the Navy projects a most likely total ship end cost of $12.887 billion. This includes the cost of construction, government furnished equipment, and design funding of $3.3 billion for non-recurring engineering which is the investment in the 11 ship class design (not just the lead ship of the class, CVN 78). Current shipyard construction cost estimates are consistent with this Navy estimate from 2 years ago.”

Partager cet article