ANAO releases damning report into ADF MRH90 program

The ANAO report into the MRH program point towards the definition phase of the project as the main cause of the delays. (NHI)

 

June 26 2014   by australianaviation.com.au

 

The Australian National Audit Office (ANAO) has released a damning report into the acquisition and service introduction of the NHI/Australian Aerospace MRH90 helicopter which was acquired under Project AIR 9000 Phases 2, 4 & 6.

 

The acquisition of the MRH90 for all three phases of the project – to acquire an additional squadron of helicopters under Phase 2, to replace the S-70A-9 Black Hawks in service under Phase 4, and to replace Navy’s Sea Kings under Phase 6 – was a key component of the ADF’s Helicopter Strategic Master Plan which sought to reduce the number of helicopter types in ADF service from nine to five, and thus realise greater training, support and sustainment efficiencies.

 

Read full article

Partager cet article
Repost0

commentaires

Présentation

  • : RP Defense
  • : Web review defence industry - Revue du web industrie de défense - company information - news in France, Europe and elsewhere ...
  • Contact

Recherche

Articles Récents

Categories