US Air Force KC-46 Tanker Programme

 

March 27, 2012 defense-aerospace.com

 (Source: Government Accountability Office; issued March 26, 2012)

 

KC-46 Tanker Aircraft: Acquisition Plans Have Good Features but Contain Schedule Risk

 

The KC-46 program has established its acquisition strategy for development and production, including total cost, procurement quantities, and key milestone dates. The program is using a $4.4 billion fixed-price incentive (firm target) development contract that provides contractor incentives to control costs and limits the government’s liability for increased costs over a certain amount.

While estimated development costs are currently $900 million higher than the February 2011 contract award amount, the government’s share of these extra costs is limited to about $500 million. The program has identified key performance parameters, but has not yet fully implemented the metrics for tracking their achievement.

There is broad agreement that KC-46 schedule risk is a concern. In GAO’s assessment, significant concurrency, or overlap, among development and production activities add risk to the program. The Air Force and contractor have assessed overall schedule risk as moderate, citing concerns about software and the ability to complete development flight testing on time.

Further, the DOD’s chief testing official finds the testing schedule not executable as currently planned. While designing a new tanker using a modified commercial platform is not as technically challenging as a more revolutionary weapon system, the program still faces some technical risks, including technologies that have not yet been demonstrated during flight.

The KC-46 program’s acquisition strategy provides a good framework for meeting GAO’s knowledge-based best practices, and generally adheres to defense policy guidance and recent acquisition reform legislation. DOD waived the requirement for a preliminary design review before the program began system development and demonstration, but this design review is planned for March 2012.

Although the program’s three critical technologies have not yet achieved the level of maturity indicated in best practices, they have reached a level of maturity consistent with DOD policy.

Given that the KC-46 is one of only a few major programs in recent years to use a fixed-price incentive contract and the importance of tanker replacement to national security, rigorous monitoring of the program’s progress will be essential.


Click here for the full report (44 pages in PDF format) on the GAO website.

Partager cet article
Repost0

commentaires

Présentation

  • : RP Defense
  • : Web review defence industry - Revue du web industrie de défense - company information - news in France, Europe and elsewhere ...
  • Contact

Recherche

Articles Récents

Categories